Squamish - Jimmy Jimmy (Judd) Slough Culvert Replacement
Federal contribution
$1.4M
$1,442,336
Federal share80%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- District Municipality of Squamish
- Construction start
- Jan 10, 2022(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Oct 31, 2023
Also in Squamish
- Brennan Park Recreation Centre Retrofit and Upgrade$11.8M
- Squamish - Brennan Park Recreation Centre Building Envelope Upgrade$5.7M
- Squamish - Mamquam Wastewater Treatment Plant Upgrade$4.0M
- Squamish - Xwu'nekw Park Sea Dike at Mamquam Blind Channel$2.2M
- Squamish River Dike Raising - Upper Jimmy Jimmy (Judd) Slough$2.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59826 in the federal list. How to read these figures.