Squamish - Mamquam Wastewater Treatment Plant Upgrade
Federal contribution
$4.0M
$4,031,496
Federal share40%
of $10.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 15, 2023
20242025
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- District Municipality of Squamish
- Construction start
- Sep 6, 2023(actual)
- Construction end
- Oct 22, 2025(actual)
Also in Squamish
- Brennan Park Recreation Centre Retrofit and Upgrade$11.8M
- Squamish - Brennan Park Recreation Centre Building Envelope Upgrade$5.7M
- Squamish - Xwu'nekw Park Sea Dike at Mamquam Blind Channel$2.2M
- Squamish River Dike Raising - Upper Jimmy Jimmy (Judd) Slough$2.2M
- Squamish - Jimmy Jimmy (Judd) Slough Culvert Replacement$1.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66928 in the federal list. How to read these figures.