Water Treatment Plant and Reservoir Expansion
Federal contribution
$1.6M
$1,587,438
Federal share33%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
201020112012201320142015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Battleford
- Construction start
- May 10, 2010(actual)
- Construction end
- Mar 3, 2015(actual)
Against the original forecast
- Construction start11 months lateforecast Jun 22, 2009
- Construction end4 weeks earlyforecast Mar 31, 2015
Also in Battleford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26258 in the federal list. How to read these figures.