Back to projects

Town of Battleford Lagoon Upgrades and Expansion

Battleford, Saskatchewan

completeWastewaterGIS
Federal contribution
$2.1M
$2,106,000
Federal share40%

of $5.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 5, 2019
202020212022
Built

Approved 2 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Battleford
Construction start
May 27, 2020(actual)
Construction end
Feb 15, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 1, 2020
  • Construction end3 months lateforecast Nov 30, 2021

Also in Battleford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54498 in the federal list. How to read these figures.