Town of Battleford Lagoon Upgrades and Expansion
Federal contribution
$2.1M
$2,106,000
Federal share40%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 5, 2019
202020212022
Built
Approved 2 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Battleford
- Construction start
- May 27, 2020(actual)
- Construction end
- Feb 15, 2022(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 1, 2020
- Construction end3 months lateforecast Nov 30, 2021
Also in Battleford