Back to projects

Town of Battleford - North Saskatchewan River Truss Bridges

Battleford, Saskatchewan

completeActive TransportationCVRIS
Federal contribution
$1.4M
$1,387,320
Federal share40%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 6, 2021
202220232024
Built

Approved 7 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Battleford
Construction start
Mar 18, 2021(actual)
Construction end
Jan 31, 2024(actual)

Against the original forecast

  • Construction start8 months earlyforecast Dec 1, 2021
  • Construction end2 months earlyforecast Mar 31, 2024

Also in Battleford