Weymouth Library
Federal contribution
$172,470
Federal share33%
of $517.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of the District of Digby
- Construction start
- Nov 9, 2009(actual)
- Construction end
- Jul 29, 2010(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2009
- Construction end8 months lateforecast Nov 30, 2009
Also in Digby
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26312 in the federal list. How to read these figures.