Weymouth Library

Digby, Nova Scotia

completeCultureCC Top Up
Federal contribution
$172,470
Federal share33%

of $517.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Nov 9, 2009(actual)
Construction end
Jul 29, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2009
  • Construction end8 months lateforecast Nov 30, 2009