Meadowbank Road/Ferry Road Sewer Upgrade
Cornwall, Prince Edward Island
Federal contribution
$47,961
Federal share33%
of $143.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Cornwall
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Sep 15, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Sep 1, 2009
- Construction end3 months lateforecast Jun 10, 2010
Also in Cornwall
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26406 in the federal list. How to read these figures.