Cornwall New Water Tower at Wellfield
Cornwall, Prince Edward Island
Federal contribution
$1.6M
$1,624,491
Federal share40%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 16, 2023
202420252026
Built
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Cornwall
- Construction start
- Jul 1, 2024(actual)
- Construction end
- Apr 16, 2026(actual)
Against the original forecast
- Construction end4 months lateforecast Dec 15, 2025
Also in Cornwall
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67811 in the federal list. How to read these figures.