Back to projects

Cornwall New Water Tower at Wellfield

Cornwall, Prince Edward Island

completeDrinking WaterGIS
Federal contribution
$1.6M
$1,624,491
Federal share40%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 16, 2023
202420252026
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Cornwall
Construction start
Jul 1, 2024(actual)
Construction end
Apr 16, 2026(actual)

Against the original forecast

  • Construction end4 months lateforecast Dec 15, 2025