2017 Trans-Canada Highway Extension - Cornwall Phase IIB
Cornwall, Prince Edward Island
Federal contribution
$20.5M
$20,492,100
Federal share40%
of $51.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 5, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- Jul 30, 2017(actual)
- Construction end
- Oct 20, 2020(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 3, 2017
- Construction end3 months lateforecast Jul 20, 2020
Also in Cornwall