Back to projects

Cornwall Wellfield Development

Cornwall, Prince Edward Island

completeDrinking WaterGIS
Federal contribution
$1.1M
$1,120,757
Federal share40%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 19, 2019
202020212022
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Cornwall
Construction start
Aug 24, 2020(actual)
Construction end
May 6, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast May 4, 2020
  • Construction end4 months lateforecast Dec 31, 2021

Also in Cornwall

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54459 in the federal list. How to read these figures.