Cornwall Civic Centre Renovation
Cornwall, Prince Edward Island
Federal contribution
$666,666
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Cornwall
- Construction start
- May 31, 2011(actual)
- Construction end
- Apr 30, 2012(actual)
Against the original forecast
- Construction start14 months lateforecast Apr 1, 2010
- Construction end4 months earlyforecast Aug 31, 2012
Also in Cornwall
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26431 in the federal list. How to read these figures.