Esquimalt - Archie Browning Sports Centre Upgrade

Esquimalt, British Columbia

completeRecreationCC Top Up
Federal contribution
$664,000
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Township of Esquimalt
Construction start
Jun 15, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 1, 2010