Tillicum Road Active Transportation Improvements for the Township Of Esquimalt

Esquimalt, British Columbia

completeActive TransportationATF
Federal contribution
$1.0M
$1,048,956
Federal share60%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 17, 2023
20232024
Built

Approved 5 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Township of Esquimalt
Construction start
Aug 26, 2023(actual)
Construction end
Sep 13, 2024(actual)

Against the original forecast

  • Construction start9 months lateforecast Dec 5, 2022
  • Construction end15 months lateforecast Jun 15, 2023

Also in Esquimalt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64596 in the federal list. How to read these figures.