Galloping Goose Regional Trail Section Upgrade

Esquimalt, British Columbia

completeActive TransportationISF
Federal contribution
$137,693
Federal share25%

of $550.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Capital Regional District
Construction start
Oct 1, 2009(actual)
Construction end
Feb 1, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2009
  • Construction end4 weeks earlyforecast Feb 28, 2011

Also in Esquimalt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29579 in the federal list. How to read these figures.