Sewage Lift Station #2/Storm Sewer
Federal contribution
$503,333
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Dalmeny
- Construction start
- Jun 21, 2010(actual)
- Construction end
- Oct 6, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2010
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in Dalmeny
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26550 in the federal list. How to read these figures.