Town of Dalmeny - Water Pumphouse and Reservoir Upgrades

Dalmeny, Saskatchewan

completeDrinking WaterGIS
Federal contribution
$1.3M
$1,344,928
Federal share40%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2021
202120222023
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Dalmeny
Construction start
Jun 7, 2021(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start11 months lateforecast Jul 1, 2020
  • Construction end4 months lateforecast Nov 30, 2022

Also in Dalmeny

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57427 in the federal list. How to read these figures.