New Stormwater System
Federal contribution
$757,200
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
2018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Dalmeny
- Construction start
- May 23, 2017(actual)
- Construction end
- Sep 12, 2018(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Sep 30, 2018
Also in Dalmeny
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50017 in the federal list. How to read these figures.