Revitalization of Local Roads
Federal contribution
$153,178
Federal share33%
of $459.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Lockeport
- Construction start
- Jul 23, 2009(actual)
- Construction end
- Apr 30, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2009
- Construction end6 months earlyforecast Oct 29, 2010