Back to projects

Revitalization of Local Roads

Lockeport, Nova Scotia

completeHighways and RoadsCC Top Up
Federal contribution
$153,178
Federal share33%

of $459.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Lockeport
Construction start
Jul 23, 2009(actual)
Construction end
Apr 30, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2009
  • Construction end6 months earlyforecast Oct 29, 2010

Also in Lockeport

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26575 in the federal list. How to read these figures.