Lockeport Wastewater System Upgrade

Lockeport, Nova Scotia

completeWastewaterRNIS
Federal contribution
$226,800
Federal share40%

of $567.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2025
202320242025
Built

Approved 2.3 years before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Lockeport
Construction start
Nov 25, 2024(actual)
Construction end
Apr 17, 2025(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Nov 1, 2024
  • Construction end2 weeks lateforecast Mar 31, 2025

Also in Lockeport

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65498 in the federal list. How to read these figures.