Back to projects

Wastewater UV Disinfection System - Lockeport

Lockeport, Nova Scotia

completeWastewaterRNIS
Federal contribution
$85,580
Federal share40%

of $214.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 24, 2019
2020
Built
Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Lockeport
Construction start
Jun 23, 2020(actual)
Construction end
Oct 23, 2020(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 18, 2020
  • Construction end5 weeks earlyforecast Nov 30, 2020

Also in Lockeport