Replacement of Belcher Street Water Reservoir and Watermain Extension
Federal contribution
$313,373
Federal share33%
of $940.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20122013201420152016
Built
Approved 4.3 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Kentville
- Construction start
- Mar 18, 2013(actual)
- Construction end
- Dec 20, 2013(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Jan 10, 2014
Also in Kentville
- Town of Kentville - Donald E. Hiltz Connector Road - Water, Storm & Sanitary Infrastructure$3.9M
- Town of Kentville Complete Active Transportation Network$1.5M
- Chester Avenue Water and Sewer Replacement$988.2K
- Regional Sewage Treatment Plant Upgrade$907.9K
- Kings County Active Transportation - Sidewalk Extensions/Additions$555.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26623 in the federal list. How to read these figures.