Back to projects

Chester Avenue Water and Sewer Replacement

Kentville, Nova Scotia

completeWastewaterSCF
Federal contribution
$988,218
Federal share33%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 2, 2015
2016
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Kentville
Construction start
May 2, 2016(actual)
Construction end
Oct 30, 2016(actual)

Against the original forecast

  • Construction end21 months earlyforecast Aug 1, 2018

Also in Kentville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46032 in the federal list. How to read these figures.