Upgrade to Seven Sewage Lift Stations
Federal contribution
$378,800
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of the County of Kings
- Construction start
- Sep 9, 2009(actual)
- Construction end
- Jan 12, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2009
- Construction end2 months lateforecast Oct 31, 2010
Also in Kentville
- Town of Kentville - Donald E. Hiltz Connector Road - Water, Storm & Sanitary Infrastructure$3.9M
- Town of Kentville Complete Active Transportation Network$1.5M
- Chester Avenue Water and Sewer Replacement$988.2K
- Regional Sewage Treatment Plant Upgrade$907.9K
- Kings County Active Transportation - Sidewalk Extensions/Additions$555.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26851 in the federal list. How to read these figures.