Kings County Active Transportation - Sidewalk Extensions/Additions
Federal contribution
$555,948
Federal share33%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of the County of Kings
- Construction start
- Aug 1, 2009(actual)
- Construction end
- Dec 20, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 4, 2009
- Construction end7 weeks lateforecast Oct 31, 2010
Also in Kentville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27016 in the federal list. How to read these figures.