St Anthony Street and Drury Lane Sidewalks
Federal contribution
$235,819
Federal share33%
of $707.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Annapolis Royal
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Oct 29, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 20, 2009
- Construction end12 months lateforecast Oct 15, 2009
Also in Annapolis Royal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26630 in the federal list. How to read these figures.