St Anthony Street and Drury Lane Sidewalks

Annapolis Royal, Nova Scotia

completeHighways and RoadsCC Top Up
Federal contribution
$235,819
Federal share33%

of $707.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Annapolis Royal
Construction start
Sep 14, 2009(actual)
Construction end
Oct 29, 2010(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jul 20, 2009
  • Construction end12 months lateforecast Oct 15, 2009