Highway 101 Repaving
Federal contribution
$1.2M
$1,215,000
Federal share50%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
2010
Built
Approved 3 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Apr 12, 2010(actual)
- Construction end
- May 14, 2010(actual)
Against the original forecast
- Construction start3 weeks earlyforecast May 1, 2010
- Construction end6 months earlyforecast Oct 31, 2010
Also in Annapolis Royal
- Water and Sewer Replacement - Ritchie and Grange Streets and St. Patrick's Lane$341.0K
- Deep Brook Sewage Collection System - Phase 1$310.2K
- Highway 101 - from Annapolis/Digby County Line$270.0K
- St Anthony Street and Drury Lane Sidewalks$235.8K
- Champlain Drive/Ritchie & Grange Streets Water and Sewer Upgrade$115.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35886 in the federal list. How to read these figures.