Water and Sewer Replacement - Ritchie and Grange Streets and St. Patrick's Lane

Annapolis Royal, Nova Scotia

completeDrinking WaterCC
Federal contribution
$341,000
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2009
2009
Built

Approved 7 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Annapolis Royal
Construction start
Jun 8, 2009(actual)
Construction end
Aug 28, 2009(actual)

Against the original forecast

  • Construction end19 months earlyforecast Mar 31, 2011