Sewage Treatment Plant Phase 2

Conception Bay South, Newfoundland and Labrador

completeWastewaterCC
Federal contribution
$1.9M
$1,948,889
Federal share32%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Construction start
Jul 2, 2010(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2010
  • Construction end11 months lateforecast Mar 31, 2016