Water and Sewer Upgrades

Conception Bay South, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$3.4M
$3,400,630
Federal share50%

of $6.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 14, 2017(actual)
Construction end
Aug 14, 2019(actual)

Against the original forecast

  • Construction end8 months lateforecast Nov 30, 2018

Also in Conception Bay South

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47088 in the federal list. How to read these figures.