Back to projects

Water & Sewer Upgrades

Conception Bay South, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$1.5M
$1,450,608
Federal share40%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022202320242025
Built
Program
Green Infrastructure Stream
Construction start
Jul 6, 2022(actual)
Construction end
Aug 30, 2025(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 2, 2022
  • Construction end2 months earlyforecast Oct 31, 2025

Also in Conception Bay South