Back to projects

New Sewage Treatment Plant

St. George's, Newfoundland and Labrador

completeWastewaterCC
Federal contribution
$270,017
Federal share7%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of St. George's
Construction start
Dec 1, 2011(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start17 months lateforecast Jul 1, 2010
  • Construction end11 months lateforecast Mar 31, 2016