Calm Waters Mi'kmaw Park Development Phase 2
St. George's, Newfoundland and Labrador
Federal contribution
$342,928
Federal share75%
of $457.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 16, 2020
202120222023
Built
Approved 5 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Flat Bay Band
- Construction start
- Apr 30, 2021(actual)
- Construction end
- Jun 30, 2023(actual)
Against the original forecast
- Construction start2 months earlyforecast Jul 7, 2021
- Construction end6 months lateforecast Dec 15, 2022
Also in St. George's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56779 in the federal list. How to read these figures.