New Water Storage Tank Replacement - Town of St. George's
St. George's, Newfoundland and Labrador
Federal contribution
$224,841
Federal share40%
of $562.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Georges
- Construction start
- Aug 10, 2020(actual)
- Construction end
- Jul 31, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast May 30, 2020
- Construction end3 months lateforecast Apr 30, 2021