New Water Storage Tank Replacement - Town of St. George's

St. George's, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$224,841
Federal share40%

of $562.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of St. George’s
Construction start
Aug 10, 2020(actual)
Construction end
Jul 31, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast May 30, 2020
  • Construction end3 months lateforecast Apr 30, 2021

Also in St. George's