Water and Sewer
Grand Falls-Windsor, Newfoundland and Labrador
Federal contribution
$974,272
Federal share29%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Grand Falls-Windsor
- Construction start
- Jul 23, 2009(actual)
- Construction end
- Mar 15, 2017(actual)
Against the original forecast
- Construction start2 months earlyforecast Oct 1, 2009
- Construction end11 months lateforecast Mar 31, 2016
Also in Grand Falls-Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26710 in the federal list. How to read these figures.