Back to projects

Water and Sewer

Grand Falls-Windsor, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$974,272
Federal share29%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Grand Falls-Windsor
Construction start
Jul 23, 2009(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start2 months earlyforecast Oct 1, 2009
  • Construction end11 months lateforecast Mar 31, 2016

Also in Grand Falls-Windsor