Back to projects

Circular Road Area Water, Storm and Sanitary Sewer Upgrades

Grand Falls-Windsor, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$1.3M
$1,265,603
Federal share40%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
202220232024
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Grand Falls-Windsor
Construction start
Jul 5, 2022(actual)
Construction end
Jul 5, 2024(actual)

Against the original forecast

  • Construction start23 months earlyforecast Jun 1, 2024
  • Construction end14 months earlyforecast Aug 31, 2025

Also in Grand Falls-Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61051 in the federal list. How to read these figures.