Exploits Valley High Building Envelope Upgrades
Grand Falls-Windsor, Newfoundland and Labrador
Federal contribution
$1.3M
$1,253,814
Federal share80%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 13, 2021
20212022
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Newfoundland and Labrador English School District
- Construction start
- Jun 21, 2021(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Aug 16, 2021
- Construction end3 months lateforecast Dec 30, 2021
Also in Grand Falls-Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58109 in the federal list. How to read these figures.