Downtown Area Water, Storm, & Road Upgrades
Grand Falls-Windsor, Newfoundland and Labrador
Federal contribution
$1.1M
$1,122,722
Federal share40%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.5 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Grand Falls-Windsor
- Construction start
- Aug 14, 2023(actual)
- Construction end
- Oct 31, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2023
- Construction end4 months lateforecast Jul 15, 2024
Also in Grand Falls-Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65142 in the federal list. How to read these figures.