Schedule
Announced and approvedFeb 10, 2010
2011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Kindersley
- Construction start
- Sep 9, 2010(actual)
- Construction end
- Oct 15, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2010
- Construction end2 weeks earlyforecast Oct 31, 2011