Town of Kindersley-West Central Event Centre Green
Federal contribution
$454,480
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 25, 2023
202320242025
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Kindersley
- Construction start
- Apr 15, 2024(actual)
- Construction end
- Feb 28, 2025(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Mar 31, 2025