Town of Kindersley Lagoon
Federal contribution
$1.7M
$1,666,667
Federal share29%
of $5.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 26, 2019
20192020
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Town of Kindersley
- Construction start
- Jul 29, 2019(actual)
- Construction end
- Oct 1, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2019
- Construction end4 weeks lateforecast Aug 31, 2020
Also in Kindersley