Town of Kindersley Lagoon

Kindersley, Saskatchewan

completeWastewaterNRP
Federal contribution
$1.7M
$1,666,667
Federal share29%

of $5.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 26, 2019
20192020
Built

Approved 5 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Town of Kindersley
Construction start
Jul 29, 2019(actual)
Construction end
Oct 1, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2019
  • Construction end4 weeks lateforecast Aug 31, 2020

Also in Kindersley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52719 in the federal list. How to read these figures.