Waterline Extension-Water, Minto and Mowatt Streets
Federal contribution
$393,033
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Shelburne
- Construction start
- May 19, 2010(actual)
- Construction end
- Sep 30, 2010(actual)
Against the original forecast
- Construction start9 months lateforecast Aug 4, 2009
- Construction end2 months lateforecast Jul 31, 2010
Also in Shelburne
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26823 in the federal list. How to read these figures.