Wastewater facility upgrade

Shelburne, Nova Scotia

completeWastewaterCWWF
Federal contribution
$1.2M
$1,182,604
Federal share50%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Shelburne
Construction start
Dec 14, 2017(actual)
Construction end
Feb 12, 2020(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Dec 28, 2017
  • Construction end7 weeks earlyforecast Mar 31, 2020

Also in Shelburne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47269 in the federal list. How to read these figures.