Sewage Treatment Plant - Phase 2
Federal contribution
$216,259
Federal share33%
of $648.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of the District of Shelburne
- Construction start
- Jan 5, 2011(actual)
- Construction end
- Oct 28, 2011(actual)
Against the original forecast
- Construction start19 months lateforecast Jun 1, 2009
Also in Shelburne
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27179 in the federal list. How to read these figures.