Robie Street Re-Construction
Federal contribution
$74,530
Federal share33%
of $223.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201120122013201420152016
Built
Approved 5.3 years before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Amherst
- Construction start
- Aug 9, 2011(actual)
- Construction end
- Oct 28, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 20, 2011
- Construction end8 weeks lateforecast Aug 31, 2011
Also in Amherst
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26940 in the federal list. How to read these figures.