Robie Street Re-Construction

Amherst, Nova Scotia

completeWastewaterCC Top Up
Federal contribution
$74,530
Federal share33%

of $223.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201120122013201420152016
Built

Approved 5.3 years before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Amherst
Construction start
Aug 9, 2011(actual)
Construction end
Oct 28, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 20, 2011
  • Construction end8 weeks lateforecast Aug 31, 2011

Also in Amherst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26940 in the federal list. How to read these figures.