Back to projects

Energy Retrofit to Municipal Complex

Kentville, Nova Scotia

completeGreen EnergyCC Top Up
Federal contribution
$296,667
Federal share33%

of $890.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
May 4, 2010(actual)
Construction end
Oct 28, 2011(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 1, 2009
  • Construction end3 months lateforecast Jul 15, 2011

Also in Kentville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26965 in the federal list. How to read these figures.