Landfill Closure
Federal contribution
$534,000
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of the District of Lunenburg
- Construction start
- Jun 9, 2010(actual)
- Construction end
- Dec 3, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 15, 2010
- Construction end4 weeks earlyforecast Dec 31, 2010
Also in Bridgewater