Reconstruction of Dorset Street
Federal contribution
$545,000
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of Port Hope
- Construction start
- Oct 19, 2009(actual)
- Construction end
- Dec 3, 2010(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Dec 31, 2010
Also in Port Hope
- Upgrades to Port Hope Water Pollution Control Plant$4.9M
- Joint Operations Centre$1.7M
- Dorset Street Standpipe Replacement - Phase 1$1.4M
- Construction of a New Seniors/Multipurpose Community Centre as an addition at the Town Park Recreation Centre$1.2M
- Sanitary Sewer Twinning of the gravity sewer from Hope Street to the Sewage Treatment Plant to mitigate by-pass during wet weather events$772.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27078 in the federal list. How to read these figures.