New Westminster - Streets & Sidewalks Revitalization

New Westminster, British Columbia

completeHighways and RoadsCC Top Up
Federal contribution
$2.7M
$2,660,169
Federal share33%

of $8.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of New Westminster
Construction start
Apr 15, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Sep 24, 2009

Also in New Westminster

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27084 in the federal list. How to read these figures.