Back to projects

Sapperton Combined Sewer Separation

New Westminster, British Columbia

completeWastewaterCWWF
Federal contribution
$3.3M
$3,326,172
Federal share50%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018201920202021
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of New Westminster
Construction start
Aug 1, 2017(actual)
Construction end
Mar 1, 2021(actual)

Against the original forecast

  • Construction end13 months earlyforecast Mar 31, 2022

Also in New Westminster