New Westminster - Urban Reforestation and Biodiversity Enhancement Initiative

New Westminster, British Columbia

completeDisaster MitigationCVRIS
Federal contribution
$1.4M
$1,396,990
Federal share80%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2021
2022202320242025
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of New Westminster
Construction start
May 30, 2022(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start6 months lateforecast Nov 30, 2021